Service Projects - Electricity ELECTRICITY INSTALLATION IS DONE! Project Requirements: MOSTLY DONE. Thank you Margaret, Chris, Wayne and sons for the work you've done on the chapel electricity. We still have the upstairs to do. Project
Constraints:
Amazing story of how He works: we had planned a work weekend. It was postponed because we weren't ready - didn't have power to the building. Then all of a sudden in comes Margaret and Chris telling us about their friend Wayne and his son and son-in-law who all do electricity. Chris and Margaret said Waynd & Sons could do the electricity in a weekend. Well. . . long story short . . . they did.
Execution Plan (pdf of chapel): Detailed
Electricity Plan Install
screen porch Project Title: Electricity Installation Project Date: Sunday, April 19, 2008 throuth Monday, April 28, 2008. Architect: Wayne Meyer Coordinator: Josh Construction Foreman: Electricians:
Lead Cook (Friday evening, Saturday Lunch, Saturday evening): Margaret Lead Cook (Saturday breakfast, Saturday break): Logistics Coordinator: Safety: Clean-up Supervisor: Devotions: Photographer: |
|||||||
![]() |
|||||||||